Subcontract change orders (SCOs)

After a change order is approved, you can create an SCO with the potential change order (PCO) items that affect the subcontractor.

The SCO includes a banner that displays:

  • Cost - Original contract: The original value of the contract.
  • Cost - Changes to date: The total applied cost from the previous SCOs for the contract.
  • Cost - This change: The total applied cost from the current SCO.
  • Cost - Contract to this CO: The original contract value plus the total applied cost from the previous SCOs and the current SCO.
  • Time - Original contract: The original substantial date of the contract.
  • Time - Changes to date: The total number of approved days from the previous SCOs for the contract.
  • Time - This change: The number of approved days from the current SCO.
  • Time - Contract to this CO: The original substantial date plus the total number of approved days from the previous SCOs and the current SCO.

SCOs for the same contract automatically have consecutive sequence numbers. You can manage PCO items and edit approved days only for the SCO with the highest sequence number.