Change order requests (CORs)
A COR is used for tracking requests for changes to the original contract between the general contractor and the project owner. You can link multiple potential change orders (PCOs) to a COR.
On the Change Order Request tab, the banner displays:
- Amount - Requested: The total (Budget) Proposed Amount from the linked PCOs.
- Amount - Approved: The total (Budget) Approved Amount from the linked PCOs.
- Days - Requested: The total number of requested days from the Information panel.
- Days - Approved: The total number of approved days from the Information panel.
The Change Order Requests module displays the requested days for unlocked records and the approved days for locked records.
- In the project menu, click Financials > Change Order Requests.
You can create CORs that group multiple PCOs together and submit them to the owner for approval. In the Information panel of the COR, you can track several dates:
- Initiated Date: The date on which the COR is created.
- Required Date: The date by which a response or decision is needed for the COR.
- Completed Date: The date on which the COR is answered or completed.
- Notice to Proceed (NTP) Date: The date on which the work is scheduled to start.
- Executed Date: The date on which the legal document for the COR is signed.
- Field permissions aren't enforced in the Create dialog but are enforced in the full record.
- Required fields are marked with an asterisk.
- On the navigation toolbar, click add_circle (Create).
- If autonumbering is off, enter the record number.
- In the Initiated Date field, enter or select a date.
- Enter a description for the COR.
- Click Create.
- In the Information panel, enter the record details.
- To change the workflow status, select an option from the list.
- In the Requested Days field, enter the number of additional days that are needed to complete the work in the change order.
- In the Reference field, enter any reference information such as a file or record.
- To add an assignment, click Add in the Assigned To section, select the name, and then set a due date.
- To add a courtesy copy, click Add in the Courtesy Copies section, and then select the name.
- On the Change Order Request tab, add the PCOs.
- On the Comments tab, enter a comment, click link (Links) to link items, and then click (Send).
- On the Contact Info tab, select the main company contacts.
- To search for or create a company, click (Search) in the company field.
- To add a contact, click the contact field, and then select or invite a contact.
- To set who has access to the COR, click group (Sharing), and then select an option.
- To link an item to the COR, click link (Links), click (Add), and then select the item type.
- To save the changes and keep the COR open, click save (Save).
This field isn't updated by the linked PCOs.
—Or—
To save the changes and close the COR, click arrow_back Done.
- In the tile or list view, on the record, click more_horiz (More) > Copy.
- If autonumbering is off, enter the record number.
- In the Initiated Date field, enter or select a date.
- Edit the description.
- Click Copy.
—Or—
Open the record, and then click content_copy (Copy) on the navigation toolbar.
The new COR includes the details from the Information panel and the Contract Info tab but doesn't include the linked PCOs.
On the Change Order Request tab, you can link PCOs to the COR. The grid, which is read-only, displays the prime contract change order (PCCO) that each PCO is linked to.
- A PCO can be linked to one COR at a time.
- If a PCO is linked to a PCCO that's doesn't have the highest sequence number for the contract, the PCO can't be added to a COR.
- If a PCO is linked to a COR, the PCO is visible in the record to all users regardless of the company that's associated with the PCO items.
- On the PCO row, click chevron_right (Open).
- Click Add.
- In the Search dialog, select the checkbox for the PCO, and then click Select.
- Select the checkbox for the PCO.
- Click Remove.
In the Information panel, the Approved Days field automatically displays the total number of approved days from the linked PCOs. If this field is unlocked, you can enter a different number.
- Click lock (Locked) by the field.
- Click lock_open (Unlocked) by the field.
The field is recalculated automatically based on the linked PCOs.
- If the Approved Days field is locked, click lock (Locked).
- In the field, enter the number.