Record syncing

This feature is available if the ERP integration is configured for the portfolio account.

If your ProjectSight project is linked to an ERP project, you can sync the following record types to the linked project:

  • Budget
  • Contracts
  • Potential change orders (PCOs) *
  • Purchase orders (POs)
  • Subcontract change orders (SCOs) *

* Only available for the Viewpoint Vista integration

  • Syncing for PCOs, and SCOs is only available for the Viewpoint Vista integration.
  • You can sync locked records to Viewpoint Spectrum and Viewpoint Vista.
  • You must have the related feature permission for the record type.

Syncing budget items

Budget items are sent automatically to the ERP based on the workflow status that was configured during the ERP integration setup.

  • When a budget item or any of its associated interactions are linked to the ERP, the budget grid displays the link icon (link) is displayed next to the item.
  • For the Viewpoint Vista integration, the budget grid displays the contract item that's linked to a budget code in the Contract Item column.
  • Unit-based and hour-based budget codes are supported for the Viewpoint Vista integration but not the Viewpoint Spectrum integration.
  • For the Viewpoint Vista integration, units of measure are added automatically to the ProjectSight Unit Of Measure list in the financial settings. If a unit of measure is deleted in Viewpoint Vista, it is also deleted from ProjectSight.

Manually syncing records

You can manually sync a record when it hasn't been sent yet or when a sync error occurred.

  • Manual syncing is supported for the Viewpoint Vista integration.
  • For PCOs, update the record in ProjectSight, and the changes will be synced to the ERP. For the other record types, you must update the information in ProjectSight and in the ERP.
  • For the Viewpoint Spectrum integration, records are synced based on the configured workflow status.