Prime contract change orders (PCCOs)

After a change order is approved, you can create a PCCO and link it to potential change orders (PCOs). A PCCO can increase the value of the prime contract or increase the number of days allotted for completing the scope of work described in the prime contract.

The PCCO includes a banner that displays:

The number of days in the Approved Days field and in the banner are calculated automatically when you link PCOs. You can also enter the number but it's overwritten by the calculated total if you link or remove a PCO. The total isn't recalculated if you change the number of approved days in a linked PCO or if you delete the linked PCO.